Registered as BEECH GROVE HOMES LIMITED. Company number 11966303. 7 payment practices reports on file, the latest for the period ending 30 September 2026, filed 29 October 2026.

31days on average to pay

  • Within 30 days
  • 31 to 60 days
  • Over 60 days

In the reporting period from 1 April 2026 to 30 September 2026, Beech Grove Homes Limited reported that it took an average of 31 days to pay its suppliers' invoices. It paid 65% of invoices within 30 days, 29% in 31 to 60 days and 6% after more than 60 days. It said 34% of invoices were not paid within the agreed terms.

That average is faster than 50% of the 6,220 companies whose latest report covers a period ending since May 2025. A year earlier, in the period to 30 September 2025, the average was 27 days, so it is 4 days slower now. It reported construction contracts in this period, and said they include retention clauses.

Average days to pay, report by report

30 28 Sep 2023 21 Mar 2024 29 Sep 2024 33 Mar 2025 27 Sep 2025 27 Mar 2026 31 Sep 2026

Bars are labelled with the month the period ended. The dashed line marks 30 days.

Every report filed

PeriodFiledAverage daysWithin 30 days31 to 60Over 60Not within termsSource
Apr to Sep 2026 29 Oct 2026 31 65%29%6%34% Report
Oct 2025 to Mar 2026 24 Apr 2026 27 75%20%5%28% Report
Apr to Sep 2025 31 Oct 2025 27 74%23%3%26% Report
Oct 2024 to Mar 2025 23 Apr 2025 33 56%34%10%49% Report
Apr to Sep 2024 29 Oct 2024 29 63%33%4%40% Report
Oct 2023 to Mar 2024 23 Apr 2024 21 86%12%2%20% Report
Apr to Sep 2023 30 Oct 2023 28 66%31%3%42% Report

Source: the company's filings on Check payment practices. Contains public sector information licensed under the Open Government Licence v3.0. Figures are as filed. We do not change them.