Statement: 09759465Jan to Jun 2026
- The 30-day benchmark
- 30 days
- Its shortest standard terms
- 7 days
- Paid within 30 days
- 50%
- Paid in 31 to 60 days
- 48%
- Paid after 60 days
- 2%
- Not paid within agreed terms
- 83%
- Retention on construction contracts
- Yes
Average time to pay33days
- Within 30 days
- 31 to 60 days
- Over 60 days
In the reporting period from 1 January 2026 to 30 June 2026, Cityfibre Limited reported that it took an average of 33 days to pay its suppliers' invoices. It paid 50% of invoices within 30 days, 48% in 31 to 60 days and 2% after more than 60 days. It said 83% of invoices were not paid within the agreed terms.
That average is faster than 44% of the 6,220 companies whose latest report covers a period ending since May 2025. It reported construction contracts in this period, and said they include retention clauses.
Every report filed
| Period | Filed | Average days | Within 30 days | 31 to 60 | Over 60 | Not within terms | Source |
|---|---|---|---|---|---|---|---|
| Jan to Jun 2026 | 31 Jul 2026 | 33 | 50% | 48% | 2% | 83% | Report |
Source: the company's filings on Check payment practices. Contains public sector information licensed under the Open Government Licence v3.0. Figures are as filed. We do not change them.